  • Contract: $2,470,000
  • Client: Jordan School District
  • Duration: 4 months
Replacement of track and field venue. Project scope included field sub drainage system, asphalt paving, track surfacing, bleachers, landscaping and ADA improvements. All concrete was self performed by CWC including the bleacher foundation, sidewalks, curbs and slab paving. The new bleachers were erected in 6 weeks and included a press box and four entry ADA ramps. Randy Haslam of Jordan School District declared that the projectís penalty for failure to complete on time was burial of the contractor at the 50 yard line. CWC completed this project in just 5 months in time for the schools home coming football game.