SHIA Security and Screening: Sky Harbor

Phoenix, AZ
  • Contract: $3,831,668
  • Client: City of Phoenix Aviation
  • Duration: 14 months
This project consisted of replacing all of the existing security screening stations with new decorative metal and glass screening partitions, security cameras and exit lane technology systems. The construction activity was continuous 7 days a week, 24 hours a day. Construction was completed at all six checkpoints throughout the three terminals without disrupting airline operations. Simultaneously we constructed a bypass road and a 12,000 square foot pre-cast concrete building to accommodate new food and beverage services in the concourse. Through creative value engineering and working closely with the airlines and the FAA, we were able to transform each security checkpoint overnight without compromising airport security and allowing the airlines to function normally the following morning.